You can price the high-level Construction Programme, which allows the S-Curve to be super-imposed on the Programme.

The benefit of doing that is that when you need to change the Construction Programme, you also automatically change the S-Curve.

Super Project is an example of a programming tool that can be used for this purpose (if it still exists?) but there are other planning/programming tools that can be used to the same effect.

When you develop the Construction Programme in far greater detail, you can drill down far more accurately into the construction costs, which enables you to fine tune your cashflow...that helps with your lending from the Bank.

reply to this article | return to the front page

Next article in this thread: Re: open invitation by karmacoma9/1 15:45Thu Jan 9 15:45:27 2025

Previous thread: Last few seats left for Saturday by LH11/2 17:19Tue Feb 11 17:19:31 2025view thread