Re: open invitation

By VoR9/1 21:16Thu Jan 9 21:16:11 2025In response to Re: open invitation

Views: 543

You can price the high-level Construction Programme, which allows the S-Curve to be super-imposed on the Programme.

The benefit of doing that is that when you need to change the Construction Programme, you also automatically change the S-Curve.

Super Project is an example of a programming tool that can be used for this purpose (if it still exists?) but there are other planning/programming tools that can be used to the same effect.

When you develop the Construction Programme in far greater detail, you can drill down far more accurately into the construction costs, which enables you to fine tune your cashflow...that helps with your lending from the Bank.