Yes,

The design & construction programme needs to be monitored & amended on a regular basis.

As the project develops & becomes more intensified, the number of activities on the programme increase, as more detail is added.

These activities are all priced out & the 'S' curve adjusts itself automatically.

You need to start off with an overall Masterplan...start to finish...Level 6/Step 10 to Level 4 (EFL League Two).

Edit:

You will end with hundreds of activities on the programme, which can then be broken down into sub-programmes, as required.

Edited by VoR at 13:37:01 on 16th March 2025